New Construction relates to the expansion of the capacity of the existing main road from the Reina Beatrix Airport to the Jaraweg in Savaneta from a single carriageway (1×2) to a dual carriageway (2×2) over a distance of approximately 6 kilometers (km).

ROUNDABOUT & BRIDGE WORK MAHUMA

Utility works has continued in the south side of the roundabout. Elmar is relocating their cables to the outer side of the roundabout boundaries. As these are oil pressured cables it required specialist from the Netherlands to assist Elmar with the re-localization of these cables. Metal arch bridge over the lagoon of the same name. On the bridge runs the road and four-lane dual carriageway.

IMG-20160331-WA0015

The works for the Mahuma box culvert has started. Traffic management is a key part in this process. The access road north was authorized to close, a deviation and sign were installed. Initially the works was performed with a half, but after was authorized the road.

In the Mahuma to Sero Tijshi intersection sector the activities executed were:

a) Transport the excavated material to the areas where the material is required;
b) Install and compact of base course material;
c) Stripping and leveling works regarding the cycle path route;
d) Stripping and leveling works for the berms;
e) Built of sloop on the road edges (where needed).
f) Bitumen emulsion was applied.

ROUNDABOUT WORK INTERFERENCE SERO TIJSHI

In the Sero Tijshi intersection sector the activities executed were:
a) All planned Utility works are completed in this area;
b) Foundation works for the roundabout road, berms and center of the roundabout has been leveled and compacted.
c) Ready for asphalt.
d) Start installation of concrete curbs for Paverwoks

BOX CULVER & ROUNDABOUT WORK INTERFERENCE KIBAIMA

Construction works for the Kibaima Box Culvert has continued. The box was excavated, installed and poured.

DCIM100MEDIADJI_0005.JPG KIBAIMA ROUNDABOUT

Works from Sero Tijshi to Kibaima has continued. Most of the works performed last periods were installation of subbase and the base course layer. Near the Kibaima Box culvert there is a large gap that has been filled in layers to reach the geometric design level.
Construction works for the Kibaima Box Culvert has continued. The box was excavated, installed and poured.